Anticipated lane closure activity for the week of April 28, 2019
- SH 121 main lanes (various lanes) northbound and southbound from Bedford Road to Glade Road – Nightly closure (7 p.m. to 6 a.m.) 4/28 thru 5/2
- SH 121 main lanes (various lanes) northbound from Bedford Road to Glade Road – Daily closure (9 a.m. to 3 p.m.) 4/29 thru 5/3
- SH 121 frontage road U-turn (south-to-north) at Cheek-Sparger Road – Continuous closure 4/28 thru 5/4
- SH 121 frontage road U-turn (north-to-south) at Harwood Road – Continuous closure 5/2 thru 5/4
Various daily lane closures throughout the project limits are possible from 9:00a.m. to 3:00p.m. All closures are subject to weather and schedule changes.
SH121Mobility is a TXDOT project. For more information, please contact Stephen Ranft, mobility coordinator for the SH121 project, at 817-462-0520 and SH121mobility@gmail.com. Visit the TXDOT PROJECT TRACKER at www.txdot.gov/inside-txdot/projects/project-tracker.html