Anticipated lane closure activity for the week of March 17, 2019
- SH 121 main lanes (various lanes) northbound and southbound from Bedford Road to Glade Road DAILY closure (9 a.m. to 3 p.m.) for construction activity - closure from 3/18 thru 3/22
- Harwood Road inside lane (eastbound and westbound) under SH 121 continuously closed for construction activity – closure thru 3/22
- SH 121 frontage road U-turn (south to north/north to south) at Harwood Road continuously closed for construction activity – closure thru 3/22
- SH 121 frontage road U-turn (north to south) at Cheek-Sparger Road continuously closed for construction activity – closure 3/21 thru 3/25
- Cummings Drive at SH 121 Frontage Road continuously closed for construction activity – closure extended into March
Various daily lane closures throughout the project limits are possible from 9:00a.m. to 3:00p.m. All closures are subject to weather and schedule changes.
SH121Mobility is a TXDOT project. For more information, please contact Stephen Ranft, mobility coordinator for the SH121 project, at 817-462-0520 and SH121mobility@gmail.com. Visit the TXDOT PROJECT TRACKER at www.txdot.gov/inside-txdot/projects/project-tracker.html