Posted on April 27, 2017 at 4:52 PM by Michlynn St. John

C. Green Scaping (Green Scaping) continues working on the Phase 1 of the Boys Ranch Master Plan Project. Progress continues to be affected by the weather. Green Scaping is still focusing their efforts on the drainage portion of the project. The concrete ledge continues to be poured daily. Green Scaping plans to install a small section of stone ledge at the north end of the drainage channel. Once staff has visually inspected the stone and mortar combination, stone work will begin on the ledge.

The bridge structures and playground equipment should be in place within 3 weeks depending on the weather. Green Scaping is in the process of putting together a report regarding the bad weather days, as well as an updated project timeline. After meeting with Green Scaping and Kimley-Horn, the consensus was that the drainage channel portion of the project should be complete at the end of June. Green Scaping will be working to make sure the Boys Ranch Park is usable for the 4thFest festivities.

Disc Golf
Kimley-Horn recently met with a local disc golf representative to discuss plans of the installation of the 18-hole disc golf course. The plans currently call for a 9 hole course that spans the south end of the Boys Ranch property. Discussions are ongoing on the possible layout to incorporate all 18 holes in order to be able to host future disc golf events.