Brookwood Hills Stream and Sanitary Sewer Rehabilitation Project
Description: This project consists of erosion control to protect City infrastructure and sanitary sewer rehabilitation. The project includes the installation of gabion baskets, gabion mattresses, 6" cable-tied concrete erosion protection, removal and replacement of the sewer line, and other sewer-related items. Seven bids were received with the lowest qualified bidder being Ark Contracting Services, LLC.
Project Cost: $475,948
Funding Source(s): 2011 Stormwater General Obligation Bonds, 2011 Stormwater Certificates of Obligation Bonds
Anticipated Completion: Summer 2021